Lease Ending in 2027? A Dilapidations Timeline for Tenants

If your commercial lease ends in 2027, now is the time to start thinking about dilapidations. Many leases end on or around the traditional quarter days (25 March, 24 June, 29 September and 25 December), and tenants who leave dilapidations until the final few weeks often end up paying more, either to a contractor working against the clock or to a landlord who has priced the work themselves.

This guide sets out a practical timeline for tenants in the Midlands and North West, based on the dilapidations projects we carry out for businesses across Birmingham, Manchester and Stoke-on-Trent.

What are dilapidations?

Dilapidations are the works needed to put a property back into the condition the lease requires when you leave. They usually cover three areas: repairs, redecoration and reinstatement (removing your alterations, such as partitions, signage or added services). The landlord sets out what they believe is owed in a schedule of dilapidations, and you can either carry out the works before you leave or agree a financial settlement instead.

12 months before lease end: read your lease

  • Find your lease, any licences for alterations and any schedule of condition agreed when you moved in.
  • Check your repair, redecoration and reinstatement clauses. Some leases require redecoration in the last year of the term, using specific colours or finishes.
  • If you have a break clause, check its conditions carefully. Some breaks depend on giving vacant possession or complying with your covenants, and getting this wrong can keep you tied into the lease.
  • Speak to your surveyor or solicitor early. They can advise on your liability and whether doing the works or negotiating a settlement makes more sense.

9 to 12 months before: get the property assessed

Ask a building surveyor to prepare an assessment of likely dilapidations, or wait for the landlord’s interim schedule if one is served. At this stage it helps to bring in a contractor to walk the building and give you a realistic idea of cost and programme. We regularly price schedules for tenants so they can budget properly and decide on the best route.

6 to 9 months before: plan and price the works

  • Get firm quotations against the schedule, broken down by item so they can be compared with the landlord’s figures.
  • Arrange an asbestos survey before any strip out or reinstatement in older buildings.
  • Agree access and working hours if you will still be trading during the works.
  • Book your contractor. Quarter-day lease ends create busy periods, so leaving it late can limit your options.

3 to 6 months before: carry out the works

Most dilapidations programmes follow a similar order: strip out and removal of tenant alterations, making good, repairs to fabric and services, then flooring and redecoration. Working this way means the decoration is fresh at handover and nothing is damaged by following trades. If you are still in occupation, works can be phased or done out of hours to keep disruption down.

Final month: handover

  • Walk the property with your surveyor and record its condition with dated photographs.
  • Remove all furniture, equipment and waste so the property is clear.
  • Return keys and fobs exactly as the lease requires.
  • Keep copies of invoices, certificates and test results to support your position if a claim follows.

Doing the works vs paying a settlement

There is no single right answer. Carrying out the works yourself gives you control over cost and quality, while a settlement can suit tenants who need a clean exit or whose landlord plans to refurbish anyway. Bear in mind that a landlord’s claim for damages is generally limited to the loss in value of their interest, so it is worth getting professional advice before agreeing figures. A contractor’s itemised price is useful evidence either way.

Dilapidations contractors in the Midlands and North West

Wallace Contracts Ltd carry out end-of-lease dilapidations works for tenants and landlords, including strip out, reinstatement, repairs, flooring, decoration and electrical, gas and plumbing works. We work across Birmingham and the West Midlands, Manchester, Stoke-on-Trent and Staffordshire, and nationwide on larger projects.

If your lease ends in 2027, call us on 01782 810220 or send us your schedule for a free, itemised quote.

This article is general guidance and not legal advice. Always check your own lease and take advice from a surveyor or solicitor.